Given the following information, answer the questions about this project: ActivityExpected DurationPredecessors
- Draw the network as a Gantt chart.
- What is the critical path? Which activities have slack time?
- What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?